What visualization method should Scrum Masters/Team Coaches use to track team delivery?

  1. Burn-in chart

  2. Burn-up chart

  3. Cumulative flow diagram

  4. Gantt chart

The correct answer is: Burn-up chart

The burn-up chart is a highly effective visualization method used by Scrum Masters and Team Coaches to track team delivery. This chart displays the amount of work completed over time against the total work required to complete the project. By having both lines—the completed work and the total work—it provides a clear and intuitive visual representation of the team's progress toward their goals. One of the key advantages of the burn-up chart is that it allows teams to rapidly see how much work has been done and how much is left, which can foster motivation and provide a sense of achievement as the completed work line approaches the total work line. Additionally, the chart can accommodate scope changes easily; if new work is added, the total work line will rise, and the team can immediately assess the impact of those changes on their delivery timeline. This contrasts with other methods like the burn-in chart, which is not a standard tool used in Agile practices. The cumulative flow diagram is more focused on analyzing work in progress, and while it's essential for flow management, it does not emphasize the completed work in the same direct way as a burn-up chart. Gantt charts are commonly used in traditional project management and do not align well with the Agile principles of flexibility and iterative progress tracking. Thus, the